STEWART TUNNEL STORY |
|
© 1988 by Kim Tschudy At 6:50 a.m. December 1, 1887, the two competing crews finally saw daylight after working for nearly one year to complete a tunnel for the Chicago, Madison and Northern Railroad. The Stewart Tunnel, which is named for James Stewart of Lancashire, Pa., was the most ambitious undertaking of the entire 173.93 mile route of the CM&N Railroad. Work at the tunnel site was plagued with troubles from the beginning of construction. Stewart, who was given the contract to build the railroad line from Monroe to Madison, was killed when he was thrown from a buggy while driving over the proposed rail route. In what may have been the first workers strike in Green County, laborers went on strike in September 1887 for wages higher that the $1.50 a day they were being paid. When CM&N management didn't give in to the workers demands, many left "Tunnel City." New workers were hired at $1.75 a day, a 50-cent increase over what the first workers received when tunnel building began December 13, 1886. At the beginning, workers had only hand-operated drills to bore the 14-by-22-foot opening through the solid blue limestone hillside. Initial plans called for the use of steam -powered drills to bore the holes to hold the blasting powder, but this was changed to a compressed air drilling operation. A 48-ton steam shovel, built by the Vulcan Iron Works of Toledo, Ohio, to be used on the north face of the tunnel was hauled in piece-by-piece because of its weight. A smaller 20-ton shovel was used at the south portal. A small locomotive named "Stella," and six cars each holding two cubic yards were used to pull the limestone out of the tunnel and down to Lynn Valley to make the long fill which consumed 155,000 cubic yards of rock. On November, 15, 1887, a stream of water erupted from the roof of the tunnel, halting work for two day until the stream stopped flowing. Eventually that area of the tunnel roof had to be shored up with timbers and bricked over to prevent further cave-ins. An undated clipping from the Belleville Recorder, indicates that an explosion in the dynamite shed occurred at the tunnel site during construction. The CM&N railroad provided bunkhouses in the nearby woods for the workers so that the railroad wouldn't have to transport the workers so far. With the long work shifts the railroad was able to rent each bed twice in each 24 hour period. Due to the extreme drought during the summer of 1887, many area farmers were forced to go to work at the tunnel in order to supplement their income. It has been said that the wages earned by area farmers enabled the farmers to hang on until better times returned. During the first week of November 1887,
70 feet of progress was made on the north end of the tunnel which
the railroad claimed at the time exceeded any previous record
for tunnel driving either in the U.S. or any other country.
The weather during the winter of 1887-1888 was also a constant
problem. The north end of the tunnel had to be boarded up to
make the tunnel warmer. On January 21, 1888 the temperatures
reached lows of 36-54 degrees below zero, causing oak trees to
explode from the intense cold.. Between Monticello and Monroe
snowdrifts up to 15 feed deep blocked the tracks for several
weeks. When the two crews of tunnel builders met near the center
of the tunnel, which is built with a two degree curve, they missed
each other by half an inch on one side of the tunnel and by less
than an inch on the other side. The first train to complete the run from
Freeport to Madison steamed through the tunnel at 10 miles per
hour on Wednesday Feb. 1, 1888. The following day a train pulling
the private car of E.T. Jeffrey, general supervisor of the It was not until August 1888 that regular train service was started on the newly completed CM & N Railroad. Mrs. Matis Chrisler Ross was thought to one of be the first, if not the first passenger to regularly ride the rain. Ross, who lived near the tunnel was teaching school at Morehead School north of Belleville and would ride the three miles each day with no fare charged. The train would not come to a complete stop at Morehead School but would slow down and Mrs. Ross would get off with the help of the brakeman. This went on for about a week until someone reported this to railroad officials who then discontinued the Morehead School slowdown. The second crossing north of the tunnel is still known as Ross Crossing and there was a small depot near the crossing. At the first crossing south of the tunnel was a station known as Exeter Station which was an old IC box car which was pulled off the rails and placed near the tracks. One area resident recalls that the station has a stove in it and a bench. "If you wanted heat you built a fire." The trains, which used to pass several times a day through the Stewart Tunnel, have gone nearly extinct except for occasional attempts by various shortline operators to restore train service to the area. An engineer on one of the shortlines which
operated through the Stewart Tunnel told the story about his
conductor. "He was a good conductor and he was a good Catholic.
Each time when we stopped before entering the tunnel he would The tunnel before its completion was a
popular spot for sightseers on weekends. Now the tunnel wall
artists tell us in large blaze orange letters that "Pabst
is Best," Ronette loves Darren Forever," and "Brookfield
East is the greatest." The sound of a train whistle in the night is supposed to be a comforting sound. This was the sound of an impending death. A death we could not prevent. We are a poorer people for not being able to share with our grandchildren the sound of the train whistle in the night... |
This
site Created & Maintained by: Jim Kalrath © 1998, 1999
Changes
Last Made: July 7th, 1999